This is Theory of constrain Model Question
We have re arrange the number of hours worked to get maximum production with out idle time
See below chart
Modeling Heat Trim
Total hours 225 100 200
Per Hour Production 2 4 2
Total Production 450 400 400
New Scenario (Answer B)
Hours Transfer (15) 5 10
New Total Hours 210 105 210
Unit Produce per hour 2 4 2
Total Units 420 420 420
See here now there is no idle time in any department and production increased from 400 to 420