The answer is D
We need to rank the products to which product has a cheep cost in production and the hiest cost in parshassing.
Use the defferent between cost of pushasing and VC of production as below:
Produst A has VC 15 $ - purshase cost 21$ = 6 $ loss if purshasing
Procust B has 34$ - 42$= 8$ loss if purshsed
Product C is purshaing (given )
So synergy should make as much as it can from product B becouse it has the more loss if purshased.
Which is the all quantity needed 6000 q
And the remain capacity for product B .
Hope that helpe u.
Regards.
------------------------------