Hi! In this question, we need to add the costs that would be different in each alternative. So, Direct Materials, Direct Labor, Variable indirect and part of variable marketing costs would be added together to get the right answer.
Direct Materials = 2
Direct Labor = 2.4
Ind. Variable costs = 1.6
Part of Variable Marketing costs = (2.5*0.3) = 0.75
Maximum amount = 6.75
The part of variable marketing cost should be 0.75 and not 1.75 since the 1.75 is the amount that will be the same in both situations. So, we should 0.75 only. I hope this helps. Good luck!
------------------------------