Hi Tayba,
Budget:
300,000 units of finished goods.
product unit need 150,000 pounds of material as total = 150,000/300,000= 0.50 material per unit (Budget)
Actual:
310,000 units of finished goods = 0.48 material per unit (Actual)
310,000 * 0.48 = 148,800 (actual material as total)
to calculate t he efficiency variance :
{(Actual finished goods units* standard material per unit) - (Actual finished goods units * actual material per unit)} * standard price=
{(310,000 * 0.50) - (310,000* 0.48)} * 0.75=
{(155,000 - 148,800)} * 0.75=
6200 * 0.75= 4,650
Why 4,650 is favorable?
because the actual material per unit is less than the standard material per unit.
0.48 is less than 0.50 or 148,800 is less that 155,000
and therefore, there is some savings regarding the actual material than the planned budget material.
------------------------------
Ahmed Zolfakar
Director/Manager
Giza
Egypt
------------------------------